Scope
Full Renovation
Duration
3 Weeks
Bathroom demolition and plumbing rough-in
BEFORE
Completed premium bathroom tiling and sanitary install
AFTER: COMPLETED
Wall tiling in progress
Modern vanity basin installation
Liquid waterproofing membrane return

Photos will be added once client image approval is confirmed. To see current project examples, ask us on WhatsApp.

Project Overview

This Dubai Marina apartment bathroom had not been renovated since original construction. The original tiling was in standard beige ceramic — functional, but dated. The waterproofing membrane had failed at the floor-wall junction, causing moisture ingress to the floor below. The sanitary ware was original and showing significant age.

The owner wanted a complete renovation to a contemporary specification before letting the apartment in a competitive Marina rental market. The project involved full demolition, new waterproofing system, large-format porcelain throughout, wall-hung toilet with concealed cistern, floating vanity, frameless shower screen, and matte black fixtures.

What Was Included

🔨 Demolition

  • ✓Full tile removal (floor and all walls)
  • ✓Existing toilet, basin, shower, vanity removed
  • ✓Old waterproofing membrane removed
  • ✓All debris removed from building via service elevator

💧 Waterproofing

  • ✓Full polyurethane membrane — floor and wall returns
  • ✓Special attention to floor-wall junction and shower zone
  • ✓48-hour cure before tiling began
  • ✓Water test performed before sign-off

🔲 Tiling

  • ✓Large-format porcelain (80×80 cm) floor — warm stone tone
  • ✓80×40 cm rectified wall tile — matching palette
  • ✓Feature niche in shower wall — recessed, tiled in contrast
  • ✓Slim-profile grout — light grey

🚿 Sanitary Ware & Fixtures

  • ✓Wall-hung toilet with in-wall concealed cistern
  • ✓Wall-mounted basin on floating vanity
  • ✓Frameless glass shower screen with matte black profile
  • ✓All taps, shower set, and accessories in matte black
  • ✓Backlit LED mirror with anti-fog function

Project Timeline

NOC from building management7 working days
Material procurement5 days (tiles from Dubai stock)
Demolition1.5 days
Waterproofing + cure1 day + 2 days cure
Tiling (floor + walls)5 days
Plumbing & electrical3 days (parallel with tiling completion)
Fit-out, snagging & handover2.5 days

Total active construction: 3 weeks. Pre-construction (NOC + materials): 1.5 weeks (overlapping).

Challenges Encountered

  • Waterproofing failure behind original tiles: The original waterproofing had failed at the floor-to-wall junction. We identified this during demolition, documented it, and applied a complete new membrane system before any tiling.
  • Service elevator scheduling: The building had limited service elevator availability — we coordinated all deliveries and waste removal around the elevator schedule over 3 separate bookings.
  • Concealed cistern wall substrate: The wall required additional preparation for the in-wall cistern frame. This was identified at the assessment stage and included in the scope.

Want a similar renovation?

This project reflects a typical mid-to-premium bathroom renovation in a Dubai Marina apartment. If you have a similar project, start with a WhatsApp message and we will respond the same day.

💬 Request a Quote on WhatsApp
Explore

Related Resources

Want a Similar Renovation?

This project is representative of our standard full bathroom renovation service. Message us with your bathroom details and we will plan your project.

Bathroom Renovation Project — Technical Standards & Quality Guide

Executing professional Bathroom Renovation Project in Dubai requires strict compliance with local construction laws, manufacturer guidelines, and community regulations. In Dubai Marina, residential utilities and structures are exposed to specific environmental demands. We deliver complete diagnostic audits, preventative maintenance, and custom installations en route from our central depot in Al Quoz, ensuring that your home remains safe and efficient.

A key challenge in the high-rise residential towers of Dubai Marina is the complex central building chilled water loops and shared MEP riser blocks. Balancing actuator valves, sanitizing ducts in tight ceiling voids, and ensuring balcony drains do not clog and flood apartments are major priorities.

For high-quality results in Bathroom Renovation Project, our certified engineering crew follows standardized procedures. If we are cleaning AC coils, we utilize biodegradable, anti-bacterial agents that wash away sand without corroding aluminum fins. For plumbing modifications, we use premium PPR/PEX piping and run pressure verification audits to check joint integrity. In case of renovation jobs, coving, liquid membranes, and structural anchors are selected to withstand local humidity and support loads safely.

Regulatory Approvals & DEWA Compliance

All structural, MEP, and electrical works in Dubai Marina must meet the regulatory requirements of developer management associations (including Emaar, Nakheel, and Dubai Properties) and municipal offices. Before commencing any major renovation or electrical modification, our Al Quoz desk coordinates NOC applications directly. This ensures that electrical loads match DEWA standards, avoiding panel trips, cable overloads, and local penalties.

Why Choose Fixer Guy in Dubai Marina

Fixer Guy provides high-quality, direct-work services designed for Dubai's premium neighborhoods. We do not apply quick fixes; instead, our in-house engineers use specialized scanners, acoustic detectors, and digital manifolds to identify the root cause of failures. We manage material sourcing and direct transport from our central depot in Al Quoz, coordinating clearances and gate passes directly to deliver a smooth, hassle-free on-site experience.

Home Maintenance & Care Checklist

  • AC Filter Washes: Wash filters every two weeks to prevent dust resistance and keep cooling airflow high.
  • RCD Trip Tests: Test the distribution board earth leakage breaker monthly to verify active shock protection.
  • Valves & Connections: Inspect under-sink angle valves for minor signs of corrosion or scale scale buildup.
  • Waterproofing Checks: Inspect balcony and rooftop membrane seals annually before winter rainfall begins.
  • Sand Filter Clearing: Regularly check and backwash villa main water line filters to prevent particulate entry.

Our Central Logistics Depot in Al Quoz

Operating from our central depot in Al Quoz, Dubai, Fixer Guy maintains a fleet of service vehicles stocked with premium OEM components, copper pipes, armored cables, and specialized testing equipment. This central base allows us to deploy certified plumbers, electricians, handymen, and AC technicians to Dubai Marina, Jumeirah, Palm Jumeirah, Arabian Ranches, and JVC within minutes.

To secure long-term property protection, check our customizable Annual Maintenance Contract (AMC) packages, or browse our dedicated guides on AC Repair Dubai and Emergency Plumbing.

Frequently Asked Questions

How long does the diagnostic survey take?

Standard maintenance and diagnostic checks take between 1 to 2 hours. For comprehensive renovations or waterproofing leaks scans, we complete a site check and provide a detailed plan within 24 hours.

Do you supply materials directly?

Yes, we supply premium, manufacturer-approved replacement components en route from our central depot in Al Quoz, backed by a comprehensive warranty to ensure long-term durability and peace of mind.

Need home services in Dubai? Message us 👋
💬